1 . Consider Award of Bid for Curb and Gutter Related to
Capital Street Projects
Adjournment
Mary A. N � 1 , City Secretary
Posted 1992 at 5.'0( .M.
BID TABULATION— CITY OF WYLIE— BID NO. 93 —02, CURB AND GUTTER CONTRACT
OCTOBER 21, 1992-2:00 P.M.
BID AMOUNT
DAYS TO
BIDDER CURB DRIVEWAY SIDEWALK MOVE-IN MOVE-IN COMMENTS
Bolen Construction 8.00/L.F. $700.00 Ea. 3.00/S.F. $350.00 10 Days
JRJ Paving 10.25/L.F. $500.00 Ea. 2.80/S.F. $650.00 10 Days
Holley & Son 10.50/L.F. , $590.00 Ea. 2.69/S.F. 3 Days
Ballard Contracting 10.93/L.F. $827.00 Ea. 5.28/S.F. $900.00 10 Days
NOTE: The above bid is a fixed rate contract for a one year period. Assuming current requirements of 4,300 linear
feet of curb and gutter, 28 driveway approachs and 200 square feet of sidewalk on Birmingham, Oak and Jackson
total costs would be as follows:
Bolen — $54,600.00; JRJ — $58,635.00; Holley —$62,208.00; Ballard — $71,211.00
BID TABULATION — CITY OF WYLIE — BID NO. 93 —02, CURB AND GUTTER CONTRACT
OCTOBER 21,1992-2:00 P.M.
BID AMOUNT
DAYS TO
BIDDER CURB DRIVEWAY SIDEWALK MOVE-IN MOVE-IN COMMENTS
Bolen Construction 8.00/L.F. $700.00 Ea. 3.00/S.F. $350.00 10 Days
JRJ Paving 10.25/L.F. $500.00 Ea. 2.80/S.F. $650.00 10 Days
Holley & Son 10.50/L.F. . $590.00 Ea. 2.69/S.F. 3 Days
Ballard Contracting 10.93/L.F. $827.00 Ea. 5.28/S.F. $900.00 10 Days
NOTE: The above bid is a fixed rate contract for a one year period. Assuming current requirements of 4,300 linear
feet of curb and gutter, 28 driveway approachs and 200 square feet of sidewalk on Birmingham, Oak and Jackson
total costs would be as follows:
Bolen — $54,600.00; JRJ — $58,635.00; Holley —$62,208.00; Ballard — $71,211.00